MMK Group launches construction of forge and foundry at cost of over RUB 14 billion

Mekhano-Remontny Kompleks (MRK, a leading equipment manufacturer that is part of MMK Group) plans to build a state-of-the-art, import-substituting production facility to manufacture forged working rolls for cold-rolling mills, forged backup rolls for cold- and hot-rolling mills, as well as large-sized forgings. Investment in the project will exceed RUB 14 billion. The project will create over 700 jobs, more than half of which will be high-productivity positions. The new facility will have a capacity of around 24 thousand tonnes of products per year.

The first phase of the project will be carried out in the second quarter of 2025, with the project scheduled for completion in the fourth quarter of 2026. The main customers of MRK’s new products will be large metals companies, including MMK, Severstal, NLMK, Evraz, Mechel, ChelPipe and Krasny Oktyabr.

“Foreign manufacturers currently account for more than 80% of the domestic market for forged working and backup rolls,” said MRK Director Oleg Shiryaev. “Once the project reaches full production capacity, imports will account for no more than 30% of the Russian market for forged rolls.”

The new forge and foundry will include a casting department for the production of ingots, a forging press for the production of forgings, a department for the heat treatment of forgings and finished forged rolls, and a machining department for the roughing, finishing and grinding of forged rolls.

Magnitogorsk Iron and Steel Works is the main investor in the project. In addition, MRK will receive a soft loan from the Industrial Development Fund of the Russian Federation. On the margins of the Innoprom 2023 industrial exhibition, which is currently taking place in Yekaterinburg, MRK signed an agreement with the Fund for a RUB 5 billion soft loan at 1% per annum as part of the Priority Projects programme. MRK’s Director, Oleg Shiryaev, and the Director of the Industrial Development Fund, Roman Petrutsa, signed the document in the presence of the Governor of the Chelyabinsk region, Aleksey Teksler.

Survey and design work will be carried out by the I. P. Bardin Ferrous Metallurgy Research Institute. An agreement with the Institute’s CEO, Viktor Semyonov, was also signed during the exhibition, with Russia’s Deputy Minister of Industry and Trade, Viktor Yevtukhov, in attendance.

Thanks to the financing from the Industrial Development Fund and the high quality of the design work carried out by the Bardin Institute, MRK will be able to build a new shop with a full production cycle within a very short time frame.