21 May ‘15

MMK modernises its power facilities

In May 2015, following the completion of adjustments and testing, TBM unit No 8 with a new turbine was commissioned. Not only will the upgraded TBM-8 enable blast-furnaces No 9 and No 10 to operate stably throughout the year, it will also reduce the expenditure on energy resources. In particular, steam consumption will decrease by 10-15%, making it possible to save up to 10 tonnes of steam per hour, or approximately 1,100 cu. m. of natural gas per hour.

In 2014-2015, a steam turbine and all supporting equipment (reheaters, pumps, pipelines etc.) were replaced, and repairs to a compressor were carried out. The new unit is also equipped with an Automated Control System, which enables optimal operational modes for TBM-8. Investment in the project amounted to approximately RUB 200 million, including cost of equipment, construction and installation works and the design process.

The TBM-8 driven steam turbine has been in operation since 1966 and had serious wear. This turbine did not meet the performance needs of blast-furnaces No 9 and No 10 during the spring-summer period.

The ongoing reconstruction of the blast-furnace plant aimed at increasing pig iron output requires increased blast volume and pressure, key factors in improving the efficiency and economic feasibility of blast-furnace smelting. However, reserves for this increase in blast volume and pressure were depleted, as seen during the summer period, when TBM limited blast-furnace productivity due to a gap between the actual and required blast parameters.

In 2012, specialists at OJSC MMK’s electrical supervision department developed and approved the Blast-Furnace Blast Provision Programme, which envisages replacing the TBM-8 driven steam turbine, among other initiatives. Following the development of technical proposals and tender procedures, an agreement with ZAO REP Holding (Saint-Petersburg) regarding TBM-8 reconstruction was concluded in May 2012.

The steam power plant comprises twelve turbo blowing machines providing the specified blast to the mill’s blast-furnaces needed to deliver project productivity. Productivity of each TBM amounts to approximately 4,000 cu. m. blast per minute.

Communications Department

This site uses cookies as described in our Privacy Policy and Terms of Use